DRP with RTO/RPO
Oracle NetSuite ERP with 99.7% business availability — maintenance included — and 9 business units in Mexico that keep operating even when the ERP is unavailable.
All 9 BUs run on GMT-6. Three regions reduce the chance that a single event hits them all.
Oracle recovers NetSuite. This plan secures everything else.
Oracle’s SLA (99.7% monthly) excludes scheduled maintenance, which can run around 15 h per quarter. If it counted against our 99.7%, it would use up the annual margin. That is why the target is measured as business service availability: NetSuite windows are covered by the BUs’ degraded mode.
NetSuite is not failed over
Core DR belongs to Oracle by contract. The company enforces and verifies the SLA, and claims credit when it is missed.
The BUs never stop
72 h local store-and-forward and their own folios: they sell, receive and invoice even when NetSuite does not respond.
Zero lost messages
Active-active iPaaS in two regions, persistent queues, idempotent consumers and a DLQ reviewed daily.
An own data copy
Incremental extraction ≤ 1 h and a daily immutable copy: lookups during an outage, ransomware defense and vendor exit.
Recovery Time Objective. Maximum time to restore the service.
Recovery Point Objective. Maximum data that can be lost.
Max. Tolerable Period of Disruption. The point at which impact becomes unacceptable.
Six measurable goals. "100% continuity" with an operational definition.
Zero transactions lost in integrations, and every BU able to run on its own for up to 72 h even when NetSuite is unavailable.
In scope (the company)
- NetSuite integration via iPaaS (SuiteTalk, RESTlets)
- IdP/SSO identity, DNS, WAN/SD-WAN for 9 BUs
- Own copy of NetSuite data
- CFDI 4.0 e-invoicing with PAC and host-to-host banking
- Satellite applications and Oracle SLA management
Oracle’s responsibility
- Infrastructure and database
- NetSuite application
- DR between data centers
- 99.7% monthly SLA, excluding scheduled maintenance
Out of scope (corporate BCP)
- Physical facilities continuity
- Physical security
- Human resources
- Interface defined in the activation process
Without business owners signing the BIA, RTO/RPO are just IT numbers.
Sponsored by the CEO office and led by the CIO; each BU contributes a continuity lead with authority to run in degraded mode.
Continuity Committee
CEO or CFO (sponsor), CIO (chair), COO, CISO, Legal/Compliance, Finance.
Crisis Management Team
CIO as Incident Commander, CISO, Infrastructure, ERP lead, Communications.
Recovery teams
Cloud, database, ERP, Integrations, Network and telecom, Identity and security, Service desk.
BU-01 to BU-09 leads
Run manual procedures and degraded mode at their site.
Each process is ranked by the cost of stopping for 1, 4, 24 and 72 h.
The resulting tier sets its RTO/RPO. The BIA is gathered through interviews at the 9 BUs and signed by each process owner. Tap a tier to filter the inventory.
What we own recovers in ≤ 1 h. Integrations, with RPO 0.
Each row is a component. Left of the disaster: how much data can be lost (RPO); right: how long it takes to come back (RTO) and how long the business can hold out (MTPD). Log scale.
* Oracle sets the RTO for the NetSuite core; when it goes down the strategy is not to fail over but to keep the BUs running in degraded mode. Before Phase 2 the contract must confirm the RTO/RPO of Oracle’s DR (if it is not set, that is risk R08).
"100% continuity" in integrations means:
Zero loss
Every message is acknowledged only after it is persisted in a replicated queue.
Zero effective duplicates
Idempotent consumers with a unique transaction key.
Local autonomy
Each BU stores 72 h and resends in order when the link returns.
Traceability
End-to-end correlation ID; DLQ with alerts and daily review.
Reconciliation
Source vs. ERP counts and amounts per BU after every event.
With Oracle’s SLA as the only backstop, 99.7% is not met.
Network, identity and iPaaS sit in series with NetSuite; degraded mode acts in parallel and covers a fraction c of its downtime. Move the sliders to check it.
Oracle reports a historical 99.96%, but the plan is designed against the contractual SLA, not the track record.
If NetSuite goes down, all 9 BUs keep operating.
BUs write to NetSuite through the iPaaS; if NetSuite does not respond, transactions wait in queues and local store-and-forward, and are applied in order when service returns. Pick a scenario.
Integrations
Business units
CFDI e-invoicing
Identity
Network
Own data copy
Observability
NetSuite
Boomi lets the runtime be deployed in the company’s cloud across two regions — what RTO 1 h and RPO 0 messages require. Confirmed or replaced in Phase 2.
| Criterion | Boomi (reference) | Celigo integrator.io (alternative) |
|---|---|---|
| Deployment | Own runtime cluster on AWS, Azure or GCP, or Boomi cloud | SaaS managed by Celigo |
| High availability | Multi-node cluster; can be replicated across two regions | Celigo’s responsibility, under its SLA |
| Control over RTO/RPO | High: the company decides regions, queues and failover | Medium: depends on the vendor |
| Best fit | Many custom integrations and RPO 0 required | Standard integrations and a small team |
Oracle has announced the end of SOAP in NetSuite 2028.2: every new integration is built on REST. Local store-and-forward is mandatory with any platform.
Eight scenarios. Ransomware is the worst: it also contaminates the replica.
That is why it demands immutable backups and a clean recovery environment. Tap a scenario in the probability × impact matrix.
NetSuite is not failed over
On E1, degraded mode is activated, a sev. 1 case is opened with Oracle and times are logged for the SLA claim.
Restore vs. fail over
If the damage is logical (E2, E3), failing over the iPaaS replicates the problem: fix it from a clean point.
Degraded mode first
In any scenario, BUs switch on store-and-forward at minute 0 to protect data while decisions are made.
No BU stops for more than 15 min, even if NetSuite takes hours.
Only the CIO (or a designated deputy) declares a major contingency; the on-call lead activates degraded mode without waiting for that declaration. Play the timeline.
Escalation matrix
Alert or degradation
IT on-call, service desk
Confirmed Tier 0/1 outage
Technical leads, ERP lead
Risk of exceeding RTO or cyberattack
CIO, CISO, Crisis Team
Declared disaster or customer/regulator impact
Sponsor, CEO office, Legal, Communications
Return to normal operation
10 runbooks
The test that validates the plan: disconnecting NetSuite for all 9 BUs.
NetSuite cannot be failed over, so what gets tested is the continuity around it. The program scales from tabletop exercises to the full test once a year.
The cycle of every test
If the IdP goes down, so does email. Channels don’t depend on the ERP.
One spokesperson per audience and updates at committed times. Printed directory, also kept in an offline vault, reviewed every quarter.
9 months. Certified in July 2027 with a full NetSuite disconnection.
7 phases and 4 gates; no phase moves on until its gate is approved. F3 and F4 overlap by four weeks so runbooks are written on the real infrastructure. Tap a phase.
A phase closes only when every item is checked.
Check items to see progress per phase. Includes the operational checklist for use during an incident.
The biggest risk isn’t technical: the business not validating RTO/RPO.
Or the plan going stale after year one. Eleven risks, each with an owner and a mitigation.
Eight indicators a month. Two matter to the business.
End-to-end availability and lost transactions, which must be 0.
ISO 22301
BIA, continuity strategy, plans, exercises and management review.
ISO/IEC 27001:2022
A.5.29 security during disruption · A.5.30 ICT readiness for continuity · A.8.13 backup · A.8.14 redundancy.
NIST SP 800-34
Methodological reference for BIA and IT contingency plans.
Every acronym, in one line.
Continuity that is designed, tested and measured.