Projects · ERP Dynamics & App
Digital transformation program · PMO document

ERP Dynamics & App Project.

From manual processes and siloed systems to one integrated digital operation: Microsoft Dynamics 365 for 300 users and the Movilform mobile platform connected to the ERP for waste traceability.

$0
MXN total program CAPEX
0
users on a single ERP
0
Jan 2027 → Dec 2028
0
monthly ERP availability
0
cycle time in critical processes
0
operations and IT incidents
01The program in 60 seconds

Three phases, one goal: an operation connected end to end.

First the ERP from scratch, then stabilize it, then connect field operations. Tap each phase to see its place on the calendar.

M1 · Jan 2027M15 · go-liveM24 · Dec 2028
−60%

Cycle time: service order to invoice, manifest issuance and month-end close.

−50%

Operations and IT incidents versus the baseline measured in M2.

≤ 2.2 h

Of downtime per month: 99.7% end-to-end ERP service availability.

Portal

Customer self-service and digital traceability as a scored differentiator in tenders.

Planning assumption: start in January 2027 (M1). Phase 1 was not in the original scope; it is proposed as a stabilization bridge between the ERP and Movilform.

02Project Charter

Six SMART goals. Measurable from day one.

The charter authorizes the Head of IT as Program Manager within $22.0 MM MXN and 24 months. Any deviation above 5% in cost or 4 weeks on the critical path escalates to the Steering Committee.

In scope

Tap a module to see what it covers.

Out of scope

  • Payroll and core HR: integrated, not replaced.
  • Transaction history > 2 years: archived in a read-only data lake.
  • Custom development that duplicates standard functionality. Rule: adopt before you adapt.

Key assumptions

  • Microsoft SaaS (SLA 99.9%); the remaining 0.2% is the margin for network, integrations and own operations.
  • Certified partner, Success by Design methodology, fixed price per deliverable.
  • Key users at 50% from M3 to M15, with budgeted backfill.
  • Change freeze on legacy processes from M12.
Sponsor: CEOPhase 0: CFOPhase 2: COOProgram Manager: Head of IT
03Target architecture

Dynamics 365 is the core. Everything flows through one integration layer.

No application connects point to point. If Movilform or a bank fails, messages wait in a queue and the ERP keeps running. Play a service flow or simulate a failure.

A service flow · ERP ↔ Movilform

Failure simulator

0messages queued
RunningERP status
All green: messages flow through API Management, Logic Apps and Service Bus.

Tap a component

Each box in the diagram explains its role in the architecture.

04Availability budget

99.7% is not a wish. It is 131 minutes, allocated.

0.3% of a 730-hour month = 2.19 h of unplanned downtime at most. Each layer has its quota. Move the sliders and see whether the service still complies.

limit 131 min
Microsoft ≤ 44Network ≤ 45Integrations ≤ 42
End-to-end monthly availability
99.70%
Meets the 99.7% target
131min down / month
0min of headroom
≤ 4 hplanned maintenance, separate

Measured user → ERP → integrations, not just the vendor SLA. Planned windows are reported separately and outside business hours. Controls: redundant links per critical site, synthetic monitoring and queues with retry.

05Roadmap · M1 to M24

ERP live in M15. Movilform closes in M24.

The critical path is Build → Testing → Go-live. Movilform starts one month after go-live so it does not compete for key users during cutover. Drag the slider or press play.

M1January 2027

In progress

    What gets decided this month

    06CAPEX and OPEX

    $22.0 MM MXN. Every peso with an owner and a contingency.

    The partner is hired at a fixed price per deliverable so the overrun risk does not fall on the 10% contingency.

    Accounting scenario: year-1 SaaS licenses as OPEX
    Critical note. SaaS subscriptions are normally operating expense. If accounting policy does not allow capitalizing year-1 licenses ($2.8 MM), that line moves to OPEX and is reallocated to contingency or integrations. Validated with the Controller before Gate 1.

    Program split

    $22.0 MMMXN · 24 months
    Phase 0 · $19.0 MMPhase 2 · $3.0 MMPhase 1 · included in P0
    $0
    MXN of CAPEX per user (Phase 0, 300 users)

    Estimated recurring OPEX from M15

    Dynamics 365 licenses

    ~90 full, ~140 Activity, ~70 Team Members.

    Contract in MXN or hedge FX

    Partner AMS support

    Monthly hour bank with P1 SLA ≤ 1 h.

    Tender in M12

    Azure

    Integration, monitoring and storage; variable consumption.

    Alerts at 80% of budget

    Movilform

    Subscription per unit / user.

    Lock the price for 3 years

    Redundant links

    Two links per critical site.

    Required for 99.7%
    07Governance, RACI and team

    No scope, cost or date decision is made outside its forum.

    RACI matrix

    R = Responsible · A = Accountable · C = Consulted · I = Informed. Tap a role to see its load.

    Internal
    12 FTE

    Program Manager, solution architect, 2 integration analysts, data, security and 6 key users at 50% (Finance, Procurement, Warehouse, Operations, Sales, Fleet).

    Partner · peak
    14

    PM, architect, 6 functional (Finance / SCM), 4 technical (X++, Power Platform, Azure) and 2 QA.

    Movilform · Phase 2
    2

    Vendor project lead and API specialist, plus a network of 30 change agents in the business.

    08Checklists by phase

    A gate is approved only with 100% of critical items closed.

    Items marked C are critical; the rest can pass with a dated closing plan. Tick items and watch the gate status change (saved in your browser).

    0%
    Gate blocked

    09KPIs and benefits

    From the starting point to the audited M24 target.

    The −60% and −50% targets only hold if the baseline is measured in M2 with the same formula used in M24. Baseline values are planning hypotheses to be replaced by the real measurement.

    End to endAvailability measured user → ERP → integrations, not just the Microsoft SLA.

    Maintenance apartPlanned windows are reported separately and do not exceed 4 h/month, outside business hours.

    Audited by FinanceMonthly Power BI dashboard to the SteerCo; Finance audits benefits in M18 and M24.

    10Risk matrix

    The three biggest risks are controlled from M1.

    Key users, data quality and over-customization. Exposure = Probability × Impact (1–5). Tap a risk on the heat map.

    ↑ ImpactProbability →
    11Change management, compliance and closure

    Adoption is the variable that moves ROI the most.

    $0.9 MM MXN and a network of 30 change agents to reach 300 certified users before go-live, using the ADKAR model.

    🧾

    Tax

    CFDI 4.0, payment and Carta Porte supplements for waste transport, and electronic accounting.

    🌿

    Environmental

    Official waste and transport documents issued from Movilform and validated before the pilot.

    🔐

    Personal data

    Privacy notice and controls for customer data on the portal.

    🛡️

    ISO/IEC 27001:2022

    Access, encryption, event logging, suppliers; quarterly review of roles and SoD.

    Documentary deliverables

      Closure criteria · M24

      • ✓M24 KPIs measured and audited by Finance.
      • ✓Executed CAPEX within ±5% of $22.0 MM MXN.
      • ✓Operations handed over to IT with AMS and SLA in force.
      • ✓Closure record signed by the Sponsor.

      ERP + mobile app + integration: one digital operation.

      Program designed and documented by Fernando Gómez Guerrero as Program Manager.